Improve Wadsworth
TRAVEL ALERT:
Southbound Wadsworth Boulevard traffic pattern change south of I-70 (Nov. 25 - Dec. 16)
**View the Weekly Updates section below for the latest construction and travel impact information. **
Project Progress Update - November 2024
The Wadsworth Improvement Project remains on schedule, with completion expected by spring of 2026 and active construction finishing by late 2025.
Additional work was added, such as permanent improvements at the 38th Avenue intersection and extending the work to the original southern limits at 35th Avenue. This was announced in the fall of 2023 and will ensure long-term cost savings and benefits.
Today, over 75% of the project is complete, including all northbound traffic lanes on concrete pavement. Major underground utility work is wrapping up, and we're nearing completion of the concrete paving for the southbound lanes, which may finish ahead of schedule.
Project Overview
This project includes modernizing and improving Wadsworth from 35th Avenue to I-70 with efficient and safe intersection designs, safer entrances and exits for vehicles accessing businesses, a continuous sidewalk on the west, and a bike/pedestrian path on the east side of Wadsworth from 35th Avenue to the Clear Creek Trail.
The project will construct a new safe and efficient intersection at 44th Avenue called a continuous flow intersection (CFI). The CFI makes the best use of land for maximum traffic flow, while prioritizing safety. A second CFI will be installed at 38th Avenue. The project is expected to be complete in spring 2026.
A larger version of the above project overview map is provided on this page.