Designing a Replacement for Our Outdoor Pool

Share Designing a Replacement for Our Outdoor Pool on Facebook Share Designing a Replacement for Our Outdoor Pool on X (formerly Twitter) Share Designing a Replacement for Our Outdoor Pool on Linkedin Email Designing a Replacement for Our Outdoor Pool link

Concept Phase Community Engagement (November 20 - December 13, 2026)

***

Anderson Outdoor Pool, located within Anderson Park, originally opened in 1979 and has been open to the community annually in the summers since. Despite a facelift in 2008, Anderson Pool and the foundation it’s built on remain mostly original to its 1979 construction, and its aging infrastructure is nearing the end of its functional life.

In 2026, city team members are working with Farnsworth Group, Counsilman-Hunsaker, BHA Design, and Wember Inc. on the design of the replacement outdoor pool. Design will continue into 2027 with anticipated completion of the design phase in summer 2027.


What are some of the issues with the current Pool?

  • Infrastructure:
    • Wall between family and lap pool deteriorating
    • Most of the pool walls are original to 1979, are not up to code, and are nearing the end of their lifespan
    • Family pool is on the original 1979 slab. That age, plus the high water table in Anderson Park, is causing increasing and irreparable damages to pipes and significant water leaks/waste plus the added cost for more water and chemicals
    • Electrical surges have damaged pumps, pipes, and valves.
    • Consistent flooding and shower/toilet issues due to 1970s design that does not align well with civil water system
    • Metal gutters and pool wall plaster are nearing the end of their lifespan
  • Mechanical:
    • Mechanical spaces are not up to current safety codes and need to be rebuilt for employee safety
    • Pool heater is incorrect size, causing issues to both pools
    • Water circulation issues between the slide catch and lap pools
    • Infrastructure issues are causing some of the mechanical issues
  • Explore the FAQ section to learn more details.


Participación comunitaria en la fase de concepto (20 de noviembre – 13 de diciembre de 2026)

  • Encuesta de la fase de concepto (disponible del 20 de noviembre al 13 de diciembre)

  • Jornada de puertas abiertas (Open House) el miércoles 2 de diciembre, de 6:00 p. m. a 7:30 p. m., en el Centro Recreativo (Recreation Center)

  • Celebración Navideña el sábado 5 de diciembre, de 3:00 p. m. a 6:30 p. m., en The Green


La Piscina al Aire Libre Anderson (Anderson Outdoor Pool), ubicada dentro de Anderson Park, abrió originalmente en 1979 y desde entonces ha estado abierta a la comunidad cada verano. A pesar de una renovación en 2008, la piscina Anderson y la cimentación sobre la que está construida siguen siendo en su mayoría las originales de 1979, y su infraestructura envejecida se está acercando al final de su vida útil.

En 2026, miembros del equipo de la ciudad están trabajando con Farnsworth Group, Counsilman-Hunsaker, BHA Design y Wember Inc. en el diseño de la piscina al aire libre de reemplazo. El diseño continuará durante 2027, y se prevé que la fase de diseño concluya en el verano de 2027.


¿Cuáles son algunos de los problemas de la piscina actual?

- Infraestructura:

  • El muro que separa la piscina familiar de la piscina de natación por carriles se está deteriorando.

  • La mayoría de las paredes de la piscina son originales de 1979, no cumplen con los códigos actuales y se están acercando al final de su vida útil.

  • La piscina familiar está construida sobre la losa original de 1979. La antigüedad de la losa, junto con el alto nivel freático en Anderson Park, está provocando daños cada vez mayores e irreparables en las tuberías, así como importantes fugas y desperdicio de agua, además de costos adicionales de agua y productos químicos.

  • Las sobretensiones eléctricas han dañado las bombas, tuberías y válvulas.

  • Se producen inundaciones frecuentes y problemas con las duchas y los inodoros debido al diseño de la década de 1970, que no es compatible con el sistema de drenaje y agua del sitio.

  • Las canaletas metálicas y el revestimiento de yeso de las paredes de la piscina se están acercando al final de su vida útil.

- Sistemas mecánicos:

  • Los espacios mecánicos no cumplen con los códigos de seguridad actuales y deben reconstruirse para garantizar la seguridad de los empleados.

  • El calentador de la piscina tiene una capacidad inadecuada, lo que provoca problemas en ambas piscinas.

  • Hay problemas con la circulación del agua entre la zona de recepción de la caída del tobogán y la piscina de natación por carriles.

  • Los problemas de infraestructura están causando algunos de los problemas mecánicos.

- Explore la sección de preguntas frecuentes (FAQ) para obtener más detalles.

Concept Phase Community Engagement (November 20 - December 13, 2026)

***

Anderson Outdoor Pool, located within Anderson Park, originally opened in 1979 and has been open to the community annually in the summers since. Despite a facelift in 2008, Anderson Pool and the foundation it’s built on remain mostly original to its 1979 construction, and its aging infrastructure is nearing the end of its functional life.

In 2026, city team members are working with Farnsworth Group, Counsilman-Hunsaker, BHA Design, and Wember Inc. on the design of the replacement outdoor pool. Design will continue into 2027 with anticipated completion of the design phase in summer 2027.


What are some of the issues with the current Pool?

  • Infrastructure:
    • Wall between family and lap pool deteriorating
    • Most of the pool walls are original to 1979, are not up to code, and are nearing the end of their lifespan
    • Family pool is on the original 1979 slab. That age, plus the high water table in Anderson Park, is causing increasing and irreparable damages to pipes and significant water leaks/waste plus the added cost for more water and chemicals
    • Electrical surges have damaged pumps, pipes, and valves.
    • Consistent flooding and shower/toilet issues due to 1970s design that does not align well with civil water system
    • Metal gutters and pool wall plaster are nearing the end of their lifespan
  • Mechanical:
    • Mechanical spaces are not up to current safety codes and need to be rebuilt for employee safety
    • Pool heater is incorrect size, causing issues to both pools
    • Water circulation issues between the slide catch and lap pools
    • Infrastructure issues are causing some of the mechanical issues
  • Explore the FAQ section to learn more details.


Participación comunitaria en la fase de concepto (20 de noviembre – 13 de diciembre de 2026)

  • Encuesta de la fase de concepto (disponible del 20 de noviembre al 13 de diciembre)

  • Jornada de puertas abiertas (Open House) el miércoles 2 de diciembre, de 6:00 p. m. a 7:30 p. m., en el Centro Recreativo (Recreation Center)

  • Celebración Navideña el sábado 5 de diciembre, de 3:00 p. m. a 6:30 p. m., en The Green


La Piscina al Aire Libre Anderson (Anderson Outdoor Pool), ubicada dentro de Anderson Park, abrió originalmente en 1979 y desde entonces ha estado abierta a la comunidad cada verano. A pesar de una renovación en 2008, la piscina Anderson y la cimentación sobre la que está construida siguen siendo en su mayoría las originales de 1979, y su infraestructura envejecida se está acercando al final de su vida útil.

En 2026, miembros del equipo de la ciudad están trabajando con Farnsworth Group, Counsilman-Hunsaker, BHA Design y Wember Inc. en el diseño de la piscina al aire libre de reemplazo. El diseño continuará durante 2027, y se prevé que la fase de diseño concluya en el verano de 2027.


¿Cuáles son algunos de los problemas de la piscina actual?

- Infraestructura:

  • El muro que separa la piscina familiar de la piscina de natación por carriles se está deteriorando.

  • La mayoría de las paredes de la piscina son originales de 1979, no cumplen con los códigos actuales y se están acercando al final de su vida útil.

  • La piscina familiar está construida sobre la losa original de 1979. La antigüedad de la losa, junto con el alto nivel freático en Anderson Park, está provocando daños cada vez mayores e irreparables en las tuberías, así como importantes fugas y desperdicio de agua, además de costos adicionales de agua y productos químicos.

  • Las sobretensiones eléctricas han dañado las bombas, tuberías y válvulas.

  • Se producen inundaciones frecuentes y problemas con las duchas y los inodoros debido al diseño de la década de 1970, que no es compatible con el sistema de drenaje y agua del sitio.

  • Las canaletas metálicas y el revestimiento de yeso de las paredes de la piscina se están acercando al final de su vida útil.

- Sistemas mecánicos:

  • Los espacios mecánicos no cumplen con los códigos de seguridad actuales y deben reconstruirse para garantizar la seguridad de los empleados.

  • El calentador de la piscina tiene una capacidad inadecuada, lo que provoca problemas en ambas piscinas.

  • Hay problemas con la circulación del agua entre la zona de recepción de la caída del tobogán y la piscina de natación por carriles.

  • Los problemas de infraestructura están causando algunos de los problemas mecánicos.

- Explore la sección de preguntas frecuentes (FAQ) para obtener más detalles.

  • November 2026 Project Updates and Concept Phase Community Engagement

    Share November 2026 Project Updates and Concept Phase Community Engagement on Facebook Share November 2026 Project Updates and Concept Phase Community Engagement on X (formerly Twitter) Share November 2026 Project Updates and Concept Phase Community Engagement on Linkedin Email November 2026 Project Updates and Concept Phase Community Engagement link

    Four project concept options (A, B, C, D) are now available for public review and feedback. Those concept options can be found in the posts following this one and in the "Documents" tab on this project page. The best way to provide feedback and input on the concept options is through the Concept Phase Community Survey.

    Additionally, if you'd like to learn more about the project, ask questions, and/or provide feedback in-person, please visit us at one of and the following in-person events:

    • Project Open House: Wednesday, December 2nd 6pm-7:30pm at the Wheat Ridge Recreation Center
    • Holiday Celebration: Saturday, December 5th 3pm-6:30pm at the Green at 38th

    Four project concept options (A, B, C, D) are now available for public review and feedback. Those concept options can be found in the posts following this one and in the "Documents" tab on this project page. The best way to provide feedback and input on the concept options is through the Concept Phase Community Survey.

    Additionally, if you'd like to learn more about the project, ask questions, and/or provide feedback in-person, please visit us at one of and the following in-person events:

    • Project Open House: Wednesday, December 2nd 6pm-7:30pm at the Wheat Ridge Recreation Center
    • Holiday Celebration: Saturday, December 5th 3pm-6:30pm at the Green at 38th
  • Concept A

    Share Concept A on Facebook Share Concept A on X (formerly Twitter) Share Concept A on Linkedin Email Concept A link


    Concept A has the lowest estimated construction and annual operating costs of the four concepts, with operating costs closest to those of the existing outdoor pool.

    The concept includes a climbing wall and a small water crossing activity, along with a family slide and areas for water volleyball. There would also be a splash pad outside the pool fencing available as a free amenity.

    The pool deck includes a party shelter and six shade umbrellas, while preserving and expanding the existing tree canopy.

    Estimated Construction Cost: $14.2 million–$16.7 million

    Estimated Annual Operating Cost: $566,000



    Concept A has the lowest estimated construction and annual operating costs of the four concepts, with operating costs closest to those of the existing outdoor pool.

    The concept includes a climbing wall and a small water crossing activity, along with a family slide and areas for water volleyball. There would also be a splash pad outside the pool fencing available as a free amenity.

    The pool deck includes a party shelter and six shade umbrellas, while preserving and expanding the existing tree canopy.

    Estimated Construction Cost: $14.2 million–$16.7 million

    Estimated Annual Operating Cost: $566,000


  • Concept B

    Share Concept B on Facebook Share Concept B on X (formerly Twitter) Share Concept B on Linkedin Email Concept B link

    Concept B has the second-lowest estimated annual operating cost of the four concepts.

    The concept includes a climbing wall, a family slide, an AquaZip'N (a modern rope swing), a water vortex (a circular current activity), and an area for water volleyball. There would also be a splash pad outside the pool fencing available as a free amenity.

    A larger raised party deck covered by shade sails would be added, along with five smaller cabanas and additional shaded areas throughout the facility. The design preserves and expands the existing tree canopy.

    Estimated Construction Cost: $15 million–$17.5 million

    Estimated Annual Operating Cost: $603,000


    Concept B has the second-lowest estimated annual operating cost of the four concepts.

    The concept includes a climbing wall, a family slide, an AquaZip'N (a modern rope swing), a water vortex (a circular current activity), and an area for water volleyball. There would also be a splash pad outside the pool fencing available as a free amenity.

    A larger raised party deck covered by shade sails would be added, along with five smaller cabanas and additional shaded areas throughout the facility. The design preserves and expands the existing tree canopy.

    Estimated Construction Cost: $15 million–$17.5 million

    Estimated Annual Operating Cost: $603,000


  • Concept C

    Share Concept C on Facebook Share Concept C on X (formerly Twitter) Share Concept C on Linkedin Email Concept C link

    Concept C has similar estimated construction costs to Concept B, but a higher estimated annual operating cost.

    The concept includes a large water crossing obstacle course over the lap pool and an area for water volleyball. The slide tower would feature an additional slide designed for one or two riders using an inner tube, in addition to the two body slides included in all four concepts. There would also be a splash pad outside the pool fencing available as a free amenity.

    Instead of a reservable group area, this concept includes shade sails covering the western grassy berm, along with ten shade umbrellas. The design preserves and expands the existing tree canopy.

    Estimated Construction Cost: $15 million–$17.5 million

    Estimated Annual Operating Cost: $640,000


    Concept C has similar estimated construction costs to Concept B, but a higher estimated annual operating cost.

    The concept includes a large water crossing obstacle course over the lap pool and an area for water volleyball. The slide tower would feature an additional slide designed for one or two riders using an inner tube, in addition to the two body slides included in all four concepts. There would also be a splash pad outside the pool fencing available as a free amenity.

    Instead of a reservable group area, this concept includes shade sails covering the western grassy berm, along with ten shade umbrellas. The design preserves and expands the existing tree canopy.

    Estimated Construction Cost: $15 million–$17.5 million

    Estimated Annual Operating Cost: $640,000


  • Concept D

    Share Concept D on Facebook Share Concept D on X (formerly Twitter) Share Concept D on Linkedin Email Concept D link

    Concept D has the highest estimated construction and annual operating costs of the four concepts.

    The concept includes a climbing wall, a small water crossing, and a water vortex (a circular current activity). A Flow Rider, which creates a continuous wave for surfing and bodyboarding, would be located on the west side of the facility.

    The pool deck includes a larger shaded reservable group area in the northeast corner, along with seven shade umbrellas. The design preserves and expands the existing tree canopy.

    Unlike Concepts A, B, and C, Concept D does not include a free splash pad outside the pool fencing.

    Estimated Construction Cost: $16.2 million–$18.3 million

    Estimated Annual Operating Cost: $752,000

    Concept D layout including lap pool, leisure pool, slides, a Flow Rider, and more. Concept is described in the preceding text.

    Concept D has the highest estimated construction and annual operating costs of the four concepts.

    The concept includes a climbing wall, a small water crossing, and a water vortex (a circular current activity). A Flow Rider, which creates a continuous wave for surfing and bodyboarding, would be located on the west side of the facility.

    The pool deck includes a larger shaded reservable group area in the northeast corner, along with seven shade umbrellas. The design preserves and expands the existing tree canopy.

    Unlike Concepts A, B, and C, Concept D does not include a free splash pad outside the pool fencing.

    Estimated Construction Cost: $16.2 million–$18.3 million

    Estimated Annual Operating Cost: $752,000

    Concept D layout including lap pool, leisure pool, slides, a Flow Rider, and more. Concept is described in the preceding text.

  • October 2026 Updates: Save the Dates for Upcoming Feedback Opportunities on Concept Options

    Share October 2026 Updates: Save the Dates for Upcoming Feedback Opportunities on Concept Options on Facebook Share October 2026 Updates: Save the Dates for Upcoming Feedback Opportunities on Concept Options on X (formerly Twitter) Share October 2026 Updates: Save the Dates for Upcoming Feedback Opportunities on Concept Options on Linkedin Email October 2026 Updates: Save the Dates for Upcoming Feedback Opportunities on Concept Options link
    supporting image

    The project team is developing initial concept options and the community will be able to review and provide feedback on those options once they're ready. The options will be available for viewing and feedback online on this website and also at the following in-person events:

    • Open House: Wednesday, December 2nd 6pm-7:30pm at the Wheat Ridge Recreation Center
    • Holiday Celebration: Saturday, December 5th 3pm-6:30pm at the Green at 38th

    The project team is developing initial concept options and the community will be able to review and provide feedback on those options once they're ready. The options will be available for viewing and feedback online on this website and also at the following in-person events:

    • Open House: Wednesday, December 2nd 6pm-7:30pm at the Wheat Ridge Recreation Center
    • Holiday Celebration: Saturday, December 5th 3pm-6:30pm at the Green at 38th
  • September 2026 Update: Design Phase Begins

    Share September 2026 Update: Design Phase Begins on Facebook Share September 2026 Update: Design Phase Begins on X (formerly Twitter) Share September 2026 Update: Design Phase Begins on Linkedin Email September 2026 Update: Design Phase Begins link

    On the 8/24/2026 City Council meeting, contracts were awarded to the Farnsworth Group to serve as the lead project design firm and Wember Inc. to serve as the owner's representative firm for the project. Work on the design phase kicked off shortly thereafter and is expected to take at least 10 months. There will be additional public engagement opportunities in the Fall 2026-Winter 2027 timeframe for feedback on the concept options, and later preliminary design options.

    On the 8/24/2026 City Council meeting, contracts were awarded to the Farnsworth Group to serve as the lead project design firm and Wember Inc. to serve as the owner's representative firm for the project. Work on the design phase kicked off shortly thereafter and is expected to take at least 10 months. There will be additional public engagement opportunities in the Fall 2026-Winter 2027 timeframe for feedback on the concept options, and later preliminary design options.

  • 2025 Public Engagement Wrap: Thank You and Next Steps

    Share 2025 Public Engagement Wrap: Thank You and Next Steps on Facebook Share 2025 Public Engagement Wrap: Thank You and Next Steps on X (formerly Twitter) Share 2025 Public Engagement Wrap: Thank You and Next Steps on Linkedin Email 2025 Public Engagement Wrap: Thank You and Next Steps link
    supporting image

    As of 8/15/2025, the initial planning round of public engagement for this project has been completed and the public survey is now closed. Thank you to everyone who provided feedback through the survey, sharing your story, talking to staff at tabling events, attending presentations, and more!

    The summary report on the public engagement is in the "Anderson Pool Documents" tab and titled "Anderson Pool Replacement Public Engagement Report 2025".

    Next steps:

    • Funding the design phase in an upcoming budget year
    • Putting out a request for proposals from design firms and selecting a design firm
    • Completing the design of the replacement pool
      • This phase will include additional public engagement opportunities to hear community feedback and preferences about the replacement pool design
    • Funding the construction phase in a future budget year, based on the project design and construction estimates
    • Selecting a construction firm
    • Demoing the existing pool and building the replacement pool

    Thank you all again!

    As of 8/15/2025, the initial planning round of public engagement for this project has been completed and the public survey is now closed. Thank you to everyone who provided feedback through the survey, sharing your story, talking to staff at tabling events, attending presentations, and more!

    The summary report on the public engagement is in the "Anderson Pool Documents" tab and titled "Anderson Pool Replacement Public Engagement Report 2025".

    Next steps:

    • Funding the design phase in an upcoming budget year
    • Putting out a request for proposals from design firms and selecting a design firm
    • Completing the design of the replacement pool
      • This phase will include additional public engagement opportunities to hear community feedback and preferences about the replacement pool design
    • Funding the construction phase in a future budget year, based on the project design and construction estimates
    • Selecting a construction firm
    • Demoing the existing pool and building the replacement pool

    Thank you all again!

  • Public Tabling Dates, Times, and Locations

    Share Public Tabling Dates, Times, and Locations on Facebook Share Public Tabling Dates, Times, and Locations on X (formerly Twitter) Share Public Tabling Dates, Times, and Locations on Linkedin Email Public Tabling Dates, Times, and Locations link

    Parks and Recreation team members will be at Anderson Pool, or large city events, at the following dates/times to answer questions about the Anderson Pool and listen to community members about their thoughts regarding the future of Anderson Pool. Please come say hi if you're around at these times!


    Date Time Location
    Friday, May 30th 12pm-3pm Anderson Pool Deck
    Thursday, June 5th 12pm-3pm Anderson Pool Deck (Cancelling this date due to cool temperatures and forecasted rain)
    Wednesday, June 11th 12pm-3pm Anderson Pool Deck
    Wednesday, June 18th 5:30pm-8pm Anderson Pavilion for Performances in the Park
    Saturday, June 28th 1:30pm-8pm Anderson Park for RidgeFest
    Wednesday, July 9th 9:30am-11am Anderson Pavilion for Performances in the Park (kids event)
    Saturday, July 12th 12pm-3pm Anderson Building Main Entrance
    Saturday, August 9th 9:30am-11:30am Carnation Festival Parade 38th Ave Ames Street-to-High Court

    Parks and Recreation team members will be at Anderson Pool, or large city events, at the following dates/times to answer questions about the Anderson Pool and listen to community members about their thoughts regarding the future of Anderson Pool. Please come say hi if you're around at these times!


    Date Time Location
    Friday, May 30th 12pm-3pm Anderson Pool Deck
    Thursday, June 5th 12pm-3pm Anderson Pool Deck (Cancelling this date due to cool temperatures and forecasted rain)
    Wednesday, June 11th 12pm-3pm Anderson Pool Deck
    Wednesday, June 18th 5:30pm-8pm Anderson Pavilion for Performances in the Park
    Saturday, June 28th 1:30pm-8pm Anderson Park for RidgeFest
    Wednesday, July 9th 9:30am-11am Anderson Pavilion for Performances in the Park (kids event)
    Saturday, July 12th 12pm-3pm Anderson Building Main Entrance
    Saturday, August 9th 9:30am-11:30am Carnation Festival Parade 38th Ave Ames Street-to-High Court
  • April and May 2025 Outreach to Community Groups

    Share April and May 2025 Outreach to Community Groups on Facebook Share April and May 2025 Outreach to Community Groups on X (formerly Twitter) Share April and May 2025 Outreach to Community Groups on Linkedin Email April and May 2025 Outreach to Community Groups link

    In April and May 2025, the project team presented, or sent information, about the project to the following community groups:

    • Wheat Ridge Optimist Club
    • Wheat Ridge Business Association
    • Wheat Ridge Parks and Recreation Commission
    • Wheat Ridge IDEA (Inclusion, Diversity, Equity, and Accessibility) Committee
    • Wheat Ridge City Council

    Throughout this engagement phase, the project team will continue to reach out to other community stakeholder groups. Please reach out to Brandon (baltenburg@ci.wheatridge.co.us, 303-231-1307) if you are part of a group who may be interested in learning more!

    In April and May 2025, the project team presented, or sent information, about the project to the following community groups:

    • Wheat Ridge Optimist Club
    • Wheat Ridge Business Association
    • Wheat Ridge Parks and Recreation Commission
    • Wheat Ridge IDEA (Inclusion, Diversity, Equity, and Accessibility) Committee
    • Wheat Ridge City Council

    Throughout this engagement phase, the project team will continue to reach out to other community stakeholder groups. Please reach out to Brandon (baltenburg@ci.wheatridge.co.us, 303-231-1307) if you are part of a group who may be interested in learning more!

Page last updated: 20 Nov 2026, 12:47 PM