Improve Wadsworth

Share Improve Wadsworth on Facebook Share Improve Wadsworth on Twitter Share Improve Wadsworth on Linkedin Email Improve Wadsworth link

TRAVEL ALERTS:

Southbound Wadsworth Boulevard temporary traffic pattern south of I-70 (Nov. 25 - Dec. 16)

Until further notice, 48th Avenue west of Wadsworth is closed only in the immediate area of southbound Wadsworth. A signed detour route is provided using 47th Avenue.

**View the Weekly Updates section below for the latest construction and travel impact information. **

Project Progress Update - November 2024

Image showing construction is 75 percent complete


The Wadsworth Improvement Project remains on schedule, with completion expected by spring of 2026 and active construction finishing by late 2025.

Additional work was added, such as permanent improvements at the 38th Avenue intersection and extending the work to the original southern limits at 35th Avenue. This was announced in the fall of 2023 and will ensure long-term cost savings and benefits.

Today, over 75% of the project is complete, including all northbound traffic lanes on concrete pavement. Major underground utility work is wrapping up, and we're nearing completion of the concrete paving for the southbound lanes, which may finish ahead of schedule.

Project Overview

This project includes modernizing and improving Wadsworth from 35th Avenue to I-70 with efficient and safe intersection designs, safer entrances and exits for vehicles accessing businesses, a continuous sidewalk on the west, and a bike/pedestrian path on the east side of Wadsworth from 35th Avenue to the Clear Creek Trail.

The project will construct a new safe and efficient intersection at 44th Avenue called a continuous flow intersection (CFI). The CFI makes the best use of land for maximum traffic flow, while prioritizing safety. A second CFI will be installed at 38th Avenue. The project is expected to be complete in spring 2026.

Image of project overview map showing three lanes in both directions on Wadsworth, new traffic signals and sidewalks.,

A larger version of the above project overview map is provided on this page.

TRAVEL ALERTS:

Southbound Wadsworth Boulevard temporary traffic pattern south of I-70 (Nov. 25 - Dec. 16)

Until further notice, 48th Avenue west of Wadsworth is closed only in the immediate area of southbound Wadsworth. A signed detour route is provided using 47th Avenue.

**View the Weekly Updates section below for the latest construction and travel impact information. **

Project Progress Update - November 2024

Image showing construction is 75 percent complete


The Wadsworth Improvement Project remains on schedule, with completion expected by spring of 2026 and active construction finishing by late 2025.

Additional work was added, such as permanent improvements at the 38th Avenue intersection and extending the work to the original southern limits at 35th Avenue. This was announced in the fall of 2023 and will ensure long-term cost savings and benefits.

Today, over 75% of the project is complete, including all northbound traffic lanes on concrete pavement. Major underground utility work is wrapping up, and we're nearing completion of the concrete paving for the southbound lanes, which may finish ahead of schedule.

Project Overview

This project includes modernizing and improving Wadsworth from 35th Avenue to I-70 with efficient and safe intersection designs, safer entrances and exits for vehicles accessing businesses, a continuous sidewalk on the west, and a bike/pedestrian path on the east side of Wadsworth from 35th Avenue to the Clear Creek Trail.

The project will construct a new safe and efficient intersection at 44th Avenue called a continuous flow intersection (CFI). The CFI makes the best use of land for maximum traffic flow, while prioritizing safety. A second CFI will be installed at 38th Avenue. The project is expected to be complete in spring 2026.

Image of project overview map showing three lanes in both directions on Wadsworth, new traffic signals and sidewalks.,

A larger version of the above project overview map is provided on this page.

  • For the week of Dec. 8, 2024

    Share For the week of Dec. 8, 2024 on Facebook Share For the week of Dec. 8, 2024 on Twitter Share For the week of Dec. 8, 2024 on Linkedin Email For the week of Dec. 8, 2024 link

    Wadsworth overnight lane closures and traffic holds planned Dec. 8 - 12

    Crews will work overnight this week (Sunday, Dec. 8 - Thursday, Dec. 12 from 7 p.m. to 6 a.m. each night) to install traffic signal mast arms throughout the Wadsworth work zone from 35th Avenue to I-70. Some of the mast arms, which hold traffic signal heads and overhead signs, are over 50 feet long. Traffic holds of up to 10 minutes and lane closures are required in order to move each mast arm into place and secure it before vehicles can pass underneath the equipment.

    Since construction activities are highly dependent on weather conditions this time of year, this schedule is subject to change.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

  • For the week of Dec. 1, 2024

    Share For the week of Dec. 1, 2024 on Facebook Share For the week of Dec. 1, 2024 on Twitter Share For the week of Dec. 1, 2024 on Linkedin Email For the week of Dec. 1, 2024 link

    Work continues at the north end of the project. The two southbound Wadsworth Boulevard travel lanes are split around a work zone from the eastbound Interstate 70 off-ramp to 47th Avenue. Southbound drivers must pick a lane when approaching the traffic split south of I-70. The next traffic pattern change in this area is expected around Dec. 16.

    Crews are also working on driveway and sidewalk connections along southbound Wadsworth south of 41st Avenue.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

  • For the week of Nov. 25, 2024

    Share For the week of Nov. 25, 2024 on Facebook Share For the week of Nov. 25, 2024 on Twitter Share For the week of Nov. 25, 2024 on Linkedin Email For the week of Nov. 25, 2024 link

    No travel impacts are planned after 12 p.m. on Wednesday, Nov. 27 - Sunday, Dec. 1.

    Travel Alert: 35th Avenue closed west of Wadsworth Boulevard (Dec. 2 - 16)

    Dec. 3, 2024 Update: This underground utility work and the 35th Avenue closure have been postponed, new dates are yet to be determined

    Underground utility work along southbound Wadsworth Boulevard and across 35th Avenue requires closing 35th Avenue west of Wadsworth from Monday, Dec. 2 at 7 a.m. to Monday, Dec. 16 at 5 p.m. For about two weeks, 35th Avenue will be closed only in the immediate area of southbound Wadsworth.

    Overnight single lane closures on Wadsworth and construction noise are expected Dec. 3 – 6 from 7 p.m. to 6 a.m. An additional multi-day closure of 35th Avenue may be necessary later for asphalt paving. 35th Avenue east of Wadsworth is not impacted by this work.

    A signed detour route for local residential traffic only will be provided using 38th Avenue and Allison Street. Wadsworth businesses are open! While 35th Avenue is closed, other access points to businesses and the Edison at Wheat Ridge apartment complex will remain open at adjacent driveways and the signalized intersection at 38th Avenue and Yukon Court.

    Since construction activities are highly dependent on weather conditions this time of year, this schedule is subject to change. Any schedule changes will be posted on message boards approaching the work area.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

  • For the week of Nov. 17, 2024

    Share For the week of Nov. 17, 2024 on Facebook Share For the week of Nov. 17, 2024 on Twitter Share For the week of Nov. 17, 2024 on Linkedin Email For the week of Nov. 17, 2024 link

    TRAVEL ALERT: Southbound Wadsworth Boulevard lanes will split around a work zone for approximately three weeks starting Nov. 25

    Starting the morning of Monday, Nov. 25, the two southbound Wadsworth Boulevard travel lanes will split around a work zone from the eastbound Interstate 70 off-ramp to 47th Avenue. Southbound drivers must pick a lane when approaching the traffic split south of I-70.

    The traffic split will be in place for approximately 1,000 feet. This temporary lane configuration is necessary for approximately three weeks while the contractor works in the median area at the north end of the Wadsworth work zone. Daily lane closures are expected on northbound Wadsworth during this work operation.

    Starting at 7 p.m. on Sunday, Nov. 24, southbound Wadsworth will be reduced to a single lane overnight (until 6 a.m. on Monday) so crews can move traffic into the new alignment.

    Progress updates will be posted on this web page. All work is weather-dependent. Any schedule changes will be posted on message boards approaching the work area.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

Page last updated: 05 Dec 2024, 10:36 AM