Improve Wadsworth

Share Improve Wadsworth on Facebook Share Improve Wadsworth on Twitter Share Improve Wadsworth on Linkedin Email Improve Wadsworth link

TRAVEL ALERTS (more information under Weekly Updates)

Until further notice, 48th Avenue west of Wadsworth is closed only in the immediate area of southbound Wadsworth. A signed detour route is provided using 47th Avenue.

35th Avenue (west side) closed at Wadsworth Dec. 16 - 23

**View the Weekly Updates section below for the latest construction and travel impact information. **

Project Progress Update - December 2024

Image showing construction is 75 percent complete


The Wadsworth Improvement Project remains on schedule, with completion expected by spring of 2026 and active construction finishing by late 2025.

Additional work was added, such as permanent improvements at the 38th Avenue intersection and extending the work to the original southern limits at 35th Avenue. This was announced in the fall of 2023 and will ensure long-term cost savings and benefits.

More than 75% of the project is complete, including nearly all of the concrete paving. Increased work activity on 38th Avenue west of Wadsworth is expected in early 2025.

Project Overview

This project includes modernizing and improving Wadsworth from 35th Avenue to I-70 with efficient and safe intersection designs, safer entrances and exits for vehicles accessing businesses, a continuous sidewalk on the west, and a bike/pedestrian path on the east side of Wadsworth from 35th Avenue to the Clear Creek Trail.

The project will construct a new safe and efficient intersection at 44th Avenue called a continuous flow intersection (CFI). The CFI makes the best use of land for maximum traffic flow, while prioritizing safety. A second CFI will be installed at 38th Avenue. The project is expected to be complete in spring 2026.

Image of project overview map showing three lanes in both directions on Wadsworth, new traffic signals and sidewalks.,

A larger version of the above project overview map is provided on this page.

TRAVEL ALERTS (more information under Weekly Updates)

Until further notice, 48th Avenue west of Wadsworth is closed only in the immediate area of southbound Wadsworth. A signed detour route is provided using 47th Avenue.

35th Avenue (west side) closed at Wadsworth Dec. 16 - 23

**View the Weekly Updates section below for the latest construction and travel impact information. **

Project Progress Update - December 2024

Image showing construction is 75 percent complete


The Wadsworth Improvement Project remains on schedule, with completion expected by spring of 2026 and active construction finishing by late 2025.

Additional work was added, such as permanent improvements at the 38th Avenue intersection and extending the work to the original southern limits at 35th Avenue. This was announced in the fall of 2023 and will ensure long-term cost savings and benefits.

More than 75% of the project is complete, including nearly all of the concrete paving. Increased work activity on 38th Avenue west of Wadsworth is expected in early 2025.

Project Overview

This project includes modernizing and improving Wadsworth from 35th Avenue to I-70 with efficient and safe intersection designs, safer entrances and exits for vehicles accessing businesses, a continuous sidewalk on the west, and a bike/pedestrian path on the east side of Wadsworth from 35th Avenue to the Clear Creek Trail.

The project will construct a new safe and efficient intersection at 44th Avenue called a continuous flow intersection (CFI). The CFI makes the best use of land for maximum traffic flow, while prioritizing safety. A second CFI will be installed at 38th Avenue. The project is expected to be complete in spring 2026.

Image of project overview map showing three lanes in both directions on Wadsworth, new traffic signals and sidewalks.,

A larger version of the above project overview map is provided on this page.

  • For the week of Dec. 22. 2024

    Share For the week of Dec. 22. 2024 on Facebook Share For the week of Dec. 22. 2024 on Twitter Share For the week of Dec. 22. 2024 on Linkedin Email For the week of Dec. 22. 2024 link

    No work is planned from Tuesday, Dec. 24 - Wednesday, Dec. 1.

    Northbound lane closures are possible on Dec. 23. 35th Avenue is expected to reopen by the end of the day on Dec. 23.


  • For the week of Dec. 15, 2024

    Share For the week of Dec. 15, 2024 on Facebook Share For the week of Dec. 15, 2024 on Twitter Share For the week of Dec. 15, 2024 on Linkedin Email For the week of Dec. 15, 2024 link

    New dates: 35th Avenue closed west of Wadsworth Boulevard (Dec. 16 - 23)

    To prepare for underground utility work, crews will work overnight on Sunday, Dec. 15 to restripe Wadsworth Boulevard near 35th Avenue. By making minor adjustments to the traffic pattern in this area, the contractor will be able to work for longer periods during the day instead of shorter hours overnight due to lane closure restrictions.

    Underground utility work along southbound Wadsworth and across 35th Avenue requires closing 35th Avenue west of Wadsworth from Monday, Dec. 16 at 7 a.m. to Monday, Dec. 23 at 5 p.m. 35th Avenue will be closed only in the immediate area of southbound Wadsworth. This work was originally planned to occur in early December. An additional multi-day closure of 35th Avenue may be necessary later for asphalt paving. 35th Avenue east of Wadsworth is not impacted by this work.

    A signed detour route for local residential traffic only will be provided using 38th Avenue and Allison Street. Wadsworth businesses are open! While 35th Avenue is closed, other access points to businesses and the Edison at Wheat Ridge apartment complex will remain open at adjacent driveways and the signalized intersection at 38th Avenue and Yukon Court.

    Also starting on Monday, Dec. 16, southbound Wadsworth Boulevard will be in a new traffic configuration at the north end of the work zone. The two southbound Wadsworth Boulevard travel lanes are currently split around a work zone from the eastbound I-70 off-ramp to 47th Avenue. The new traffic pattern will remove the lane split configuration by bringing the southbound left lane adjacent to the right lane. Please use caution while drivers adjust to the new configuration.

    Since construction activities are highly dependent on weather conditions this time of year, this schedule is subject to change. Any schedule changes will be posted on message boards approaching the work area.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us


  • For the week of Dec. 8, 2024

    Share For the week of Dec. 8, 2024 on Facebook Share For the week of Dec. 8, 2024 on Twitter Share For the week of Dec. 8, 2024 on Linkedin Email For the week of Dec. 8, 2024 link

    Wadsworth overnight lane closures and traffic holds planned Dec. 8 - 12

    Crews will work overnight this week (Sunday, Dec. 8 - Thursday, Dec. 12 from 7 p.m. to 6 a.m. each night) to install traffic signal mast arms throughout the Wadsworth work zone from 35th Avenue to I-70. Some of the mast arms, which hold traffic signal heads and overhead signs, are over 50 feet long. Traffic holds of up to 10 minutes and lane closures are required in order to move each mast arm into place and secure it before vehicles can pass underneath the equipment.

    Since construction activities are highly dependent on weather conditions this time of year, this schedule is subject to change.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

  • For the week of Dec. 1, 2024

    Share For the week of Dec. 1, 2024 on Facebook Share For the week of Dec. 1, 2024 on Twitter Share For the week of Dec. 1, 2024 on Linkedin Email For the week of Dec. 1, 2024 link

    Work continues at the north end of the project. The two southbound Wadsworth Boulevard travel lanes are split around a work zone from the eastbound Interstate 70 off-ramp to 47th Avenue. Southbound drivers must pick a lane when approaching the traffic split south of I-70. The next traffic pattern change in this area is expected around Dec. 16.

    Crews are also working on driveway and sidewalk connections along southbound Wadsworth south of 41st Avenue.

    Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

Page last updated: 19 Dec 2024, 01:17 PM