2026 Playground Replacements at Fruitdale Park and Prospect Park
Project Complete – Both Playgrounds Are Now Open!
November 25, 2026
We're excited to share that construction fencing has been removed at Prospect Park, and the new playground is officially open! This marks the completion of the 2026 playground replacement projects at Fruitdale and Prospect parks, and both playgrounds are now ready for the community to enjoy.
The new playground at Prospect Park is Wheat Ridge's first universally accessible playground, featuring accessible swings, ramps, climbing features, and poured-in-place surfacing designed to provide opportunities for children of all abilities to play together.
Thank you to everyone who participated in the planning and design process for these two playgrounds, including the students from Compass Montessori and Mountain Phoenix Community School who helped shape the new playground at Fruitdale Park. We also appreciate the community's patience and understanding as we worked through construction and delays in receiving playground components.
We hope you'll take some time to visit both parks and enjoy the new playgrounds!
Prospect Park Playground
Playground Update: Fruitdale Park Open, Prospect Park Still Closed
November 12, 2026
We're excited to share that the new playground at Fruitdale Park is officially open! Join us Thursday, November 12, at 4:15 p.m. for the rescheduled ribbon-cutting celebration.
Both Fruitdale and Prospect playground replacements have experienced delays due to playground components that were not delivered as expected. These delays pushed back the original opening dates, and we appreciate everyone's patience as we work to complete the projects.
Prospect Park's new playground remains closed while we wait for the remaining components to arrive and be installed. We don't have a confirmed opening date yet, but we're working to get the playground completed and open to the community as soon as possible. In the meantime, the existing playground on the west side of Prospect Park remains open for use.
Thank you to everyone who helped shape these new playgrounds through the community engagement process. We're excited to see Fruitdale open and look forward to welcoming everyone to the new playground at Prospect soon!

Ribbon-Cutting Event: Wednesday, October 28th at 4pm at Fruitdale Park

Project Updates: The playground options from GameTime were preferred for both park locations and both playground installation timelines have now been finalized. Completion dates are approximate:
- Fruitdale: 9/18-10/26
- Prospect: 9/28-10/26