For the weeks of May 4 and May 11, 2025
Increased activity is underway between 35th and 41st avenues. Median curb and landscape wall installation continues in advance of planting activities this summer.
The new traffic signal at 41st Avenue is expected to be operational soon. Once the new signal is active, the traffic signal at 3 Acre Lane will be removed.
Crews are currently placing safety railing and irrigation throughout the entire corridor. Daily northbound lane closures continue.
Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us