For the weeks of Dec. 21 and 28, 2025

The Continuous Flow Intersections (CFIs) on Wadsworth Boulevard at both 38th Avenue and 44th Avenue are open. Please use extra caution while drivers adjust to the new traffic patterns.

A CFI is an innovative intersection design that changes the way left turns are made. Instead of waiting in the middle of the intersection, drivers making left turns will cross over before reaching the main intersection, guided by traffic signals and signs. For more information, including how to drive a CFI and what changes are coming, read the project FAQs on this page.

The contractor will be working on final signing and striping as well as other finishing work on Monday and Tuesday, Dec. 22 and 23. No work is planned Dec. 24 - Jan. 4.

All work is weather-dependent, and the schedule is subject to change.

Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

Share For the weeks of Dec. 21 and 28, 2025 on Facebook Share For the weeks of Dec. 21 and 28, 2025 on Twitter Share For the weeks of Dec. 21 and 28, 2025 on Linkedin Email For the weeks of Dec. 21 and 28, 2025 link
#<Object:0x00007fa52c4c0670>